Record the shooting day

You can record what actually happens on a shooting day — crew call, first shot, lunch, company moves, delays, completed scenes, and wrap — and see at a glance whether the day is on time and when it will wrap.

The Day tab: minutes behind and the projected wrap, the Record buttons, and planned against actual times.
The Day tab: minutes behind and the projected wrap, the Record buttons, and planned against actual times.

Anyone who logs takes can record the day, so the assistant directors and the script supervisor share one record.

Open a shooting day

  1. In a project, click On Set in the sidebar, then click Day.
  2. Choose a day from Shooting day.
    Today's shooting day opens first.

Record a moment

  1. Under Record, click the moment as it happens: Crew call, Shooting call, First shot, Lunch, Company move, Camera wrap, or Crew wrap.
    The time appears under the button. After Lunch, the button changes to Back from lunch; after Company move, it changes to Move done.
  2. To fix a time, click the button again (or click Edit next to the moment in the Log), change Time, then click Save.

When FilmKit already knows a moment — for example, the first take sets the time of the first shot, and a camera tech hold suggests a delay — it appears under Suggestions. Click Add to record it.

Record a delay

  1. Under Record, click Delay.
  2. Enter when it Started at and the Minutes lost, then choose the Cause and, if it held up one scene, the Scene.
  3. Click Save.

Delays by cause adds up the minutes lost for each cause.

Mark a scene completed

  1. Under Schedule, find the scene.
  2. Click Scene completed at the end of its row.

When every planned shot of a scene has a circled take, the scene also appears under Suggestions.

See how the day is going

The top of the page shows how many minutes the day is ahead or behind, and when you will wrap compared with the planned wrap from the call sheet. FilmKit works this out from the scene you're shooting now and the rest of the day's schedule.

Planned and actual compares each moment with the call sheet. A warning appears when the day will run longer than 12 hours from crew call, or when wrap leaves less than 11 hours of rest before the next day's call.